File #: R-19-16    Version: 1 Name:
Type: Resolution Status: Adopted
File created: 6/13/2019 In control: Albuquerque Bernalillo County Water Utility Authority
On agenda: 6/26/2019 Final action: 6/26/2019
Title: Authorizing an Agreement with PV Trails Albuquerque, LLC for Water and Sewer Service for Unit 3A of the Trails subdivision
Sponsors: Albuquerque Bernalillo County Water Utility Author
Attachments: 1. R-19-16

ALBUQUERQUE BERNALILLO COUNTY

WATER UTILITY AUTHORITY

 

 

BILL NO.                            R-19-16        |

 

 

RESOLUTION

t

Authorizing an Agreement with PV Trails Albuquerque, LLC for Water and Sewer Service for Unit 3A of the Trails subdivision

b

WHEREAS,  PV Trails Albuquerque, LLC is the Developer and owner of property located in Unit 3A of the Trails subdivision, south of Paseo Del Norte and west of Rainbow Blvd. N.W.; and

WHEREAS,  the property lies within the former New Mexico Utilities, Inc. ("NMUI") service area, outside the Water Authority's currently adopted Water Service Area; and

WHEREAS, the Water Authority’s Water and Wastewater System Expansion Ordinance requires that new service developed outside the Water Authority’s service area will incur no net expense to the Water Authority, be facilitated by a Board approved development agreement and be subject to provisions of relevant updated planning documents as approved by the City and/or County; and

BE IT RESOLVED BY THE WATER AUTHORITY:

Section 1.  PV Trails Albuquerque, LLC will obtain all permits, assurances, and approvals from the Water Authority and the City of Albuquerque development/design review process.  Construction of water and/or sewer lines and Master Plan Facilities shall be in conformance with the plans approved by the Water Authority and all applicable plans, specifications, requirements, and standards of the Water Authority.

Section 2.  The provision of water and wastewater service to the Property and the expansion of the System shall incur no net expense to the Water Authority or current ratepayers and shall be subject to Utility Expansion and Water Supply Charges current at the time of connection and as updated from time to time.

Section 3.  The provision of water and wastewater service to the Property shall be contingent upon the Developer: constructing necessary Master Plan Infrastructure; paying its proportionate share of the cost of arsenic removal and installing other improvements consisting of distribution and collector lines to tie into existing Water Authority infrastructure in the area. 

Section 4.  PV Trails Albuquerque, LLC will be responsible for close coordination of the project with the Water Authority during the design and construction phases, including the review of the design details during the design process, and the approval of specifications and contract documents.

Section 5.  The Executive Director is authorized to enter into an Agreement with PV Trails Albuquerque, LLC consistent with this Resolution and Water Authority Ordinances for the provision of water and sewer service to the Property.