Skip to main content
File #: R-21-12    Version: 1 Name:
Type: Resolution Status: Adopted
File created: 5/13/2021 In control: Albuquerque Bernalillo County Water Utility Authority
On agenda: 6/23/2021 Final action: 6/23/2021
Title: Amendment to the Approved Capital Implementation Program of the Albuquerque Bernalillo County Water Utility Authority for the Fiscal Year Ending June 30, 2022
Sponsors: Albuquerque Bernalillo County Water Utility Author
Attachments: 1. R-21-12

ALBUQUERQUE BERNALILLO COUNTY

WATER UTILITY AUTHORITY

 

 

BILL NO.                                          R-21-12                     |

 

 

RESOLUTION

t

Amendment to the Approved Capital Implementation Program of the Albuquerque Bernalillo County Water Utility Authority for the Fiscal Year Ending June 30, 2022                     

b

WHEREAS, the Capital Implementation Program is governed by the requirements established under Section 2-1-8, 2006, which provides for amendments to the approved program; and

                     WHEREAS, appropriations for the Fiscal Year ending June 30, 2022 that were previously approved under R-21-8 and R-21-9 require an amendment to add HB285 Capital Outlay Projects awarded in the 2021 State Legislative Session. 

THEREFORE, BE IT RESOLVED BY THE WATER AUTHORITY:

                     That the adjustments for the projects as stated below are hereby made.

                     State Capital Outlay Projects (Expense)                     1,657,500

                     State Grants (Revenue)                                          1,657,500