File #: R-14-9    Version: 1 Name:
Type: Resolution Status: Adopted
File created: 4/17/2014 In control: Albuquerque Bernalillo County Water Utility Authority
On agenda: 4/23/2014 Final action: 5/21/2014
Title: Appropriating Funds for the Capital Implementation Program for the Albuquerque Bernalillo County Water Utility Authority for the Fiscal Year Beginning July 1, 2014 and ending June 30, 2015
Sponsors: Albuquerque Bernalillo County Water Utility Author
Attachments: 1. R-14-9
ALBUQUERQUE BERNALILLO COUNTY
WATER UTILITY AUTHORITY


BILL NO. R-14-9 |


RESOLUTION
t
Appropriating Funds for the Capital Implementation Program for the Albuquerque Bernalillo County Water Utility Authority for the Fiscal Year Beginning July 1, 2014 and ending June 30, 2015.
b
WHEREAS, the Albuquerque Bernalillo County Water Utility Authority (Water Authority) as a political subdivision of the State of New Mexico is required to budget and account for all money received or spent in accordance with New Mexico laws; and
WHEREAS, the Board, by Ordinance, has established a budget process for the Authority; and
WHEREAS, the Budget Ordinance, requires the Executive Director to formulate an annual Capital Implementation Program budget for the Water Authority; and
WHEREAS, the Budget Ordinance requires the Water Authority Board to approve or amend and approve the Executive Director's proposed budget; and
WHEREAS, the Board has received the Capital Implementation Program Budget formulated by the Executive Director and has deliberated on it and provided public notice and input; and
WHEREAS, appropriations for the Capital Implementation Program of the Water Authority must be approved by the Board; and
WHEREAS, the appropriation of these Capital Implementation Program funds to projects with their respective purposes are timely and necessary for Water Authority to serve its customers.
BE IT RESOLVED BY THE WATER AUTHORITY:
Section 1. That the appropriations for the projects as stated below are hereby made.
Purpose Source Increase
Basic Program
Water Utility / Joint Water & Sewer Rehab Fund 628
Sanitary Sewer Pipeline Renewal
Interceptor Sewer Rehabilitation Bond Proceeds 1,000,000
Interceptor Rehab Contingency Bond Proceeds 1,400,000
Small Diameter Sewer Line
Rehabilitation Bond Proceeds 1,000,000
Small Diameter Sewer Line
Rehab Contingency Bond Proceeds 500,000
Sewer Line CCTV Inspections Bond ...

Click here for full text